With the exterior coming along, more work has started to develop on individual floors as well as details for the rooms! With all the nice spring weather, the crew has been hard at work!

  • The terrace units and plaza are finish with insulation and drywall is 90% complete.
  • The exterior sheathing, siding, trim is complete on floors 2 – 5.
  • Floors 2 & 3 drywall and painting is complete.
  • The fireplaces on the 4th floor are operational.
  • The 2nd floors, ceramic tile, wood flooring, bathroom tile, and fireplace surround tile are 80% complete.
  • The shells for the indoor pools and spa #5 are complete.
  • Pool coping stone is being installed on indoor pools.
  • 2nd floor cabinets delivered
  • 2nd and 3rd floor doors, hardware and prefinished trim ordered.
  • Mechanical room is 90% complete.
  • Electrical room is 75% complete.
  • Pool mechanical room is 50% complete.

The construction at Grand Colorado continues to move along. We can’t wait to share the most luxurious Breckenridge resort with you, your family and friends. Make sure to like us on Facebook for the most recent updates and news!