Construction Update October 6

Construction Update – October 6

October 6 Update

We are continuing to move forward with updates at Grand Colorado on Peak 8. Here is what the construction updates look like this month:

  • The second floor concrete has been poured for phase 3
  • The steel “super structure” has been concluded with the exception of a few minor details that will wrap up shortly.
  • The air conditioning for the building – the Cooling Tower has been set on the roof.
  • The 14’ back fill for the garage driveway entrance has been finished.
  • Windows and sliding doors have been installed for phase 1 of the plaza and terrace units
  • The fourth floor drywall is being installed for phase 1.
  • Phase 1 of the trim and siding work is continuing
  • Waterproofing of the pool “shell” has been completed.

The construction on Grand Colorado on Peak 8 is still underway. We are excited to share this luxury resort with you, your family and friends. Make sure to like us on Facebook for the most recent updates and news!