Construction Update – April 6

4.6.15HA mild spring has really helped the BGV construction crew keep up with the work of building the Grand Colorado on Peak 8. Things are moving fast and as the mild spring makes way to summer, progress will be swift. Here is info on the latest updates.

Construction Update – March 2015:

  • Started exterior sheathing on 3rd floor
  • Roofing insulation has started
  • Installation of scaffolding is complete
  • Exterior metal framing is complete
  • Windows and sliding door installation has started (at the residential units)
  • Interior metal framing is 90% complete (in the residential units)
  • Boilers for the building have arrived
  • Main electrical panels are being installed
  • Structural steel complete through 1st floor
  • Started concrete flatwork on 1st floor